Run a Schedule Cleanse

Cleanse and resolve flaws in your Microsoft Project or Primavera P6 schedule.

To run a schedule cleanse, complete the following steps

:
  1. Select the S1 // Projects tab.
  2. Select the project that you want to cleanse.
  3. In the Scenario Generation menu, click Cleanse Schedule.
  4. On the Cleanse Schedule dialog box, select the desired cleanse options. Click on a specific cleanse option to see the list of related issues in the right pane.

    You can include or exclude individual activities. In addition, lags (durations on relationships) can either be removed or converted to activities.

  5. Click OK to create a cleanse scenario. The scenario displays on the S1 // Projects tab Projects tree under the selected project.